The partnership between Core Scientific and AMD, announced in late July, appears far more significant than it might seem at first glance. According to my analysis, the initial 530 MW contracts could generate over $14 billion in revenue over 15 years. Here, AMD acts not just as a client but effectively as a credit guarantor for part of the Bitcoin miner's infrastructure, fundamentally changing the risk dynamics.

The deal structure is divided into two key segments: 377 MW is a direct triple-net lease for AMD, while the remaining 152 MW is allocated to an unnamed cloud provider, but with credit support from the chip manufacturer itself. This configuration significantly reduces financing costs and minimizes counterparty default risk, setting this deal apart from similar ones where tenants rely on external guarantees.

Financial Math and Margins

The average annual revenue from the agreement is estimated at approximately $0.9 billion, or about $1.8 million per megawatt. This is 5–25% below the $1.9–2.4 million per megawatt range seen in recent AI equipment hosting deals by miners. However, the key point is the margin. For the 377 MW direct lease, AMD achieves a margin close to 100%, and the blended EBITDA across the entire deal reaches 96%. This indicates that Core Scientific has found a way to monetize its infrastructure with minimal operating costs.

Core Scientific's capital expenditures for this project will amount to $11–12 million per megawatt, totaling about $6 billion. Of this, $1 billion has already been spent, and the company plans to raise the remainder through project bonds. AMD has also received warrants to purchase 30 million shares of Core Scientific at $23.47 per share, with the vesting of these options tied to achieving a target capacity of 2.5 GW.

New Trend: Chip Manufacturers as Anchor Tenants

This deal confirms a fundamental shift in the market. Previously, tenants were backed by tech giants like Google, but now AI chip manufacturers themselves—AMD, Nvidia—are willing to directly become anchor clients and support multi-year projects. Similar examples include Hut 8 allocating 704 MW to a tenant identified as Nvidia, and AMD reserving 200 MW at Riot Platforms.

Recall that Core Scientific also paid Block $41.9 million to terminate a mining chip supply contract, confirming the company's accelerated shift from pure Bitcoin mining toward AI.

Expert Opinion: The Core Scientific and AMD deal is not just a contract but a model for the entire industry's future. Miners that quickly adapt to the role of AI infrastructure operators will gain access to long-term, high-margin contracts, while their peers stuck in traditional mining risk being left behind. AMD, in turn, secures guaranteed capacity for deploying its chips, which is critical amid data center shortages.