Analysts at Bernstein have provided a detailed breakdown of the strategic alliance between Core Scientific and AMD, estimating its potential at over $14 billion in revenue over a 15-year horizon. This involves initial contracts for 530 MW, which essentially reshape the bitcoin miner's business model, turning it into a key infrastructure operator for artificial intelligence.
Deal Structure: Less Risk, More Margin
Under the agreement, announced on July 28, the contracted capacity is divided into two segments: 377 MW are structured as a direct triple-net lease for AMD, while the remaining 152 MW are intended for an unnamed cloud provider, with AMD acting as a credit guarantor. This structure, Bernstein emphasizes, significantly reduces financing costs and minimizes counterparty risks—unlike classic schemes where tenants rely on external credit support.
The option component deserves special attention: AMD has received warrants for 30 million Core Scientific shares at a price of $23.47 per share. The vesting of these rights is strictly tied to achieving an ambitious target of 2.5 GW of total capacity, which incentivizes both parties toward a long-term partnership.
The financial parameters are impressive: average annual revenue is estimated at approximately $0.9 billion, or about $1.8 million per megawatt. Although this figure is 5–25% below the $1.9–2.4 million per megawatt range seen in recent competitor deals, the deal's margin more than compensates for this. According to Bernstein, for the 377 MW of direct lease, the margin for AMD approaches 100%, while the blended EBITDA across the entire project is approximately 96%.
Capital Expenditures and Trend Confirmation
Core Scientific plans to invest $11–12 million per megawatt, totaling about $6 billion in capital expenditures. Of this, roughly $1 billion has already been spent, and the company intends to raise the remainder through project bonds. This signals high confidence in the stability of future cash flows.
This partnership is not an isolated case but part of a systemic shift. Previously, we saw Hut 8 allocate 704 MW to a tenant identified as Nvidia, and AMD reserved 200 MW at Riot Platforms. Unlike early contracts where tenants were backed by tech giants like Google, now chip manufacturers themselves are becoming anchor tenants, directly supporting multi-year projects.
It's worth recalling that Core Scientific also paid Block $41.9 million for the early termination of a mining chip supply contract—a deliberate sacrifice for accelerated diversification into the AI segment.
My comment: This deal confirms a fundamental transformation of the industry: former miners are becoming critical infrastructure for the AI economy, and chip manufacturers are willing to take on financial risks for guaranteed access to capacity. A 96% EBITDA margin is a metric that most traditional data centers can only dream of, making such alliances strategically beneficial for both parties.