On August 6, it became known that SpaceX and Tesla have finally settled on a site for their ambitious Terafab project. It will be Grimes County, Texas. Initial construction investments will amount to $16.8 billion, and the facility itself, according to Elon Musk, will become "the largest and most valuable building on Earth."
Scale and Specialization
The manufacturing complex will occupy a colossal 9.3 million square meters. A key feature is the consolidation of all stages—from chip production to packaging and testing—under one roof. This will create at least 3,000 jobs for residents of Grimes and Brazos counties.
Terafab will produce two product lines. The first is chips for edge computing and inference, which will form the foundation of Tesla Optimus robots and Cybercab robotaxis. The second is high-performance solutions for SpaceX orbital data centers, which looks like a logical step given the company's space ambitions.
The location was not chosen by chance: the plant will be situated near the Gibbons Creek Reservoir, which previously served to cool a coal-fired power plant closed in 2018. The company has committed to using exclusively this reservoir, without affecting local groundwater sources.
Deal Structure and Uncertainty
The legal framework of the project draws attention. In the SpaceX IPO prospectus, Terafab is characterized as a "general framework"—there are no binding agreements between SpaceX and Tesla. Intellectual property rights are not secured, and withdrawal from the project is possible at any time. This creates certain risks, although Intel's participation, announced in April, adds weight to the project.
The investment figures also raise questions. Initially, Musk cited $25 billion; now the talk is of $16.8 billion for the first phase. At the same time, SpaceX has acknowledged that total costs could reach $119 billion. Such a wide range suggests that the final parameters of the project have not yet been fixed.
Tax Incentives and Public Discontent
The project has already faced public backlash. Grimes County approved a full property tax exemption until 2036 in exchange for fixed payments: $10 million upfront and $20 million annually. However, after the documents were published, a discrepancy emerged: SpaceX had stated investments of $55 billion, while the contract mentioned $5 billion by 2030 and 1,800 jobs by 2035.
Local residents expressed concerns about the strain on the power grid and water consumption. In response, SpaceX committed to building its own gas-fired power plants, operating on a closed-loop water cycle, and not raising rates for other ERCOT consumers. Company lawyers calculated that, accounting for the fixed payments, the effective tax discount would be about 78%, and total payments to the county over 35 years would reach $710 million.
Initial earthworks will begin shortly, with construction starting within a few months.
My comment: Terafab is not just a factory but a strategic bet on vertical integration in a critically important industry. However, the vague legal obligations between SpaceX and Tesla, as well as the significant discrepancy between stated and documented figures, are a warning sign. Investors should closely monitor how this project develops, especially given that the SpaceX IPO prospectus has already warned of the potential commercial non-viability of orbital data centers, for which part of the chips are intended.